Natural England objects to AI datacentre as ministers eye its abolition

Natural England lodged a formal objection to a proposed 40‑megawatt artificial‑intelligence datacentre on the Avonmouth industrial site, urging Bristol City Council to refuse planning permission because of the threat it poses to protected wildlife and habitats.
The site lies within 600 metres of the Severn Estuary Special Protection Area, one of the United Kingdom’s most important migratory‑bird zones, and only 270 metres from Hallen Marsh, another designated conservation area. Natural England warned that construction could cause “disturbance and displacement” of rare and vulnerable bird species that rely on these habitats.
The Environment Agency, also facing possible abolition, added its own concerns. It highlighted the location’s placement on a high‑risk flood plain, noting that the developers had not supplied data on water‑use levels or the risk of land‑contamination pollution to controlled waters. The agency warned that, in the event of a deluge, people might not have a safe refuge.
More than 4,000 members of the public have signed objections to the Avonmouth project. Rivington Energy, the developer, said it “acknowledges the feedback received from the Environment Agency and Natural England” and is preparing a detailed environmental statement to address the comments as part of the ongoing planning process.
The Avonmouth proposal arrives amid a national drive to build AI datacentres, which the government touts as vital to economic growth. Hundreds of such facilities are planned, with over 300 waiting to connect to the electricity grid, representing roughly 73 GW of demand – almost double the United Kingdom’s peak winter electricity consumption. To accelerate delivery, the government is allowing developers to use the nationally significant infrastructure projects (NSIP) regime, which places the final decision in the hands of the Secretary of State rather than local authorities.
Louise Haigh, the de facto deputy prime minister, has recently blamed “quangos” such as Natural England and the Environment Agency for blocking development. Haigh indicated that both bodies could be scrapped, with their responsibilities transferred to ministers or devolved administrations, as part of a broader push to streamline AI datacentre construction.
Natural England, in a response to the government’s draft datacentre national policy statement, stressed that AI datacentres are a relatively new development type and that their full environmental impacts are still being understood. The agency highlighted potential over‑abstraction of water resources and the risk to rare species, urging a precautionary approach to the nationwide rollout.
Craig Bennett, chief executive of the Wildlife Trusts, warned that the threatened abolition of Natural England “is a worrying sign of an attack on environmental regulation.” He said, “Regulatory arm’s‑length bodies like Natural England are set up to implement the law of parliament. If we want decisions made about nature on the basis of science rather than the very last private corporate or vested interest that a minister has spoken to, then we need independent arm’s‑length bodies like Natural England.”
Mary Stevens, an AI campaigner with Friends of the Earth, praised Natural England’s role, stating, “Natural England was doing its job brilliantly here as an independent adviser. I would have no confidence if this was a government minister doing the work because they would not be acting independently to protect nature.”
A government spokesperson reiterated the official line, saying, “Datacentres are essential to our economy, but their development must protect the environment and benefit local communities. Developers must meet planning requirements, with local authorities assessing environmental impacts, and then deciding on local applications.”