Macquarie Point Stadium Cost Rises to $1.23 Billion, Total Project Could Reach $1.76 Billion
The cost to build Hobart’s Macquarie Point stadium has risen by $100 million to $1.23 billion, but a cascade of additional expenses — including essential precinct works, project delivery costs, and an undisclosed contingency — could push the total taxpayer commitment toward $1.76 billion, according to figures released by the Tasmanian government.
Premier Jeremy Rockliff announced the updated construction budget via social media, attributing the increase from the previous $1.13 billion estimate to high oil, materials and labour prices. The Macquarie Point Development Corporation (MPDC) also cited the war in Iran and Australia’s competitive infrastructure pipeline, including the upcoming Brisbane Olympics, as major factors. In a bid to contain costs, the MPDC said it had “value managed” the project by $100 million through design and delivery adjustments.
For the stadium to function, broader precinct works are required. Energy, water and landscaping upgrades, plus a car park described by MPDC chief executive Anne Beach as an “enabler” for the wider precinct rather than a stadium necessity, add $132 million, bringing the subtotal to $1.36 billion. Project delivery costs — consultants, MPDC staff, insurance, software and incidentals — contribute a further $183 million, lifting the figure to $1.54 billion.
A critical missing piece is the contingency allowance. The government and MPDC have declined to disclose the amount ahead of signing a building contract with construction partner BESIX Watpac. The previous $1.13 billion estimate included a $174 million contingency. Applying a similar proportion to the current $1.54 billion base would add roughly $215 million, yielding a potential total budget of $1.76 billion.
Not included in that tally is the $78.9 million Northern Access Road, a long-standing project to be funded and managed separately by Building Tasmania. Interest on additional borrowings required to cover the increased cost is also unaccounted for; a new funding facility is being established for the MPDC, and the corporation’s borrowing limit will be raised.
The state funding cap of $875 million, agreed to by Rockliff in exchange for upper house MP Bec Thomas’s vote, is effectively scrapped. Approximately $1.29 billion of the project cost will now be borne by Tasmanian taxpayers through capital and borrowings. The premier said conversations had begun with the federal government, the AFL, cricket authorities and the private sector regarding increased financial contributions.
The roof, a condition of the AFL agreement, and a cricket test rig constructed earlier this year are included in the core stadium cost. A smaller-scale roof prototype was built to test shadow impacts on cricket play. Bulk excavation and environmental monitoring are already underway at the site.
At a recent public accounts committee hearing, department secretary Kathrine Morgan-Wicks emphasized the need to understand the proposed relationship between the MPDC and the lead contractor before a final investment decision. Beach said commercial, legal and technical teams had analysed the detail submitted by BESIX Watpac and were confident the project could be delivered within the revised budget.
The new budget will be presented to cabinet by November 30 and is expected to be approved, with a construction contract to be signed in the coming weeks. “The cost has changed, but the opportunity for Tasmania has not,” Rockliff said. “Every generation has a couple of rare opportunities to change their future … for us, this is a golden one.”